Doosan DL300-3 Посібник з експлуатації - Сторінка 13
Переглянути онлайн або завантажити pdf Посібник з експлуатації для Компактний навантажувач Doosan DL300-3. Doosan DL300-3 18 сторінок. Wheel loader
IMPORTANT
If work is done on the 6th cylinder of an engine with an
EGR system, the EGR valve control cylinder must be
detached at the damper and removed.
10. Remove upper rocker cover and then the rocker arm
housing, valve bridges and pushrods.
11. Pull the cable harness out of the lower rocker cover and
remove it.
NOTE:
Take care when pulling the cable harness out of
the rocker cover: the cable terminals can be
damaged which can cause the nut securing the
cable harness to the injector to come loose.
12. Work on the adjacent cylinders. Remove upper rocker
cover, release the cable harness and the lower rocker
cover so it can be moved.
13. Remove relevant cylinder head. Be careful with the
adjacent rocker covers.
NOTE:
Mark the cylinder heads if more than one is
being removed at the same time.
NOTE:
If all cylinder heads are removed at the same
time, the turbocharger must be removed or
supported against the frame.
Installing
1.
Check the liner height as described in the work description
for Checking the liner height.
2.
Clean the cylinder head and cylinder block. Lubricate the
threads and below the heads of the cylinder head bolts.
3.
Install a new cylinder head gasket.
4.
Install the cylinder head.
Engine
Figure 12
Figure 13
FG020251
FG020252
SP002541