C Series Installation Guide
Start-Up & Test
Unpacking
Start-Up & Test
Step One:
Turn off the switches on the front of the compressor.
Step Two:
Ensure that the dryer by-pass shut-off valve is open.
Step Three:
Ensure that strainer shut-off valve is open.
Step Four:
Close outlet valve on the compressor tank.
Step Five:
Apply power to system — the purge valve my emit a hissing sound as the purge timer resets.
Step Six:
Switch on the motors. If you hear the popping sound of air escaping the relief valve, the dryer by-pass valve is closed.