Boiler cleaning and maintenance
5.Cleaning of the fan box:
-
unscrew two M8 nuts and remove the fan box lid.
-
remove ash and impurities from the fan box.
-
place back the fan box lid on two M8 screws and tighten them with two M8 nuts to
get good air tightness during operation.
Figure 8. Extraction turbulators
BioSolid 26
BioSolid 34
28
Technical instructions BioSolid
2.0. BOILER POSITIONING AND ASSEMBLY
The boiler's body is covered by the casing with an thermal insulation on wooden box
and packed in a protective PVC foil. Before placing boiler body onto its location in
the boiler room, it should be removed from palette. Boiler positioning and assembly
and building in of additional equipment must be performed by a qualified person.
We recommend that boiler is placed on a concrete base with height of 50 to 100 mm
above the floor. Boiler room must be frost-proof and well ventilated. Boiler has to be
positioned so that it can be properly connected to the chimney (see point 4.0) and
simultaneously, enabling tending of boiler and additional equipment, control during
operation, and cleaning and maintenance (see Figure 1).
WARNING!
Flammable items must not be placed on the boiler and within the minimum
distances shown in Figure 1.
Figure 1. Minimum distance from the room walls
min. 1000 mm
* - If the boiler is installed in the heating system
** - If the boiler is directly installed on the heating
Technical instructions BioSolid
Boiler positioning and assembly
min. 1000 mm*
min. 1000 mm**
min. 700 mm*
via the accumulation
system
5