DECKORATORS ALX CONTEMPORARY PRE-ASSEMBLED RAILING Інструкція з монтажу - Сторінка 2
Переглянути онлайн або завантажити pdf Інструкція з монтажу для Меблі для вулиці DECKORATORS ALX CONTEMPORARY PRE-ASSEMBLED RAILING. DECKORATORS ALX CONTEMPORARY PRE-ASSEMBLED RAILING 3 сторінки.
Railing Installation
Prior to construction:
• Check building code requirements for maximum spacing between deck surface and bottom of rail (sweep). Spacing of 3" is recommended
for 36" or 42" finished rail height.
Step 1 Measure the distance between installed posts to determine the length of the top and bottom rails. Position rail adjacent to installed
posts. The distance between the post and the first baluster should be less than 4" and equal on both ends. Mark the length on top and bottom
rails.
Step 2 Remove an additional 1/2" on both ends (1" overall) for the bracket to fit between the rail and post. Trim the top and bottom rails to
length (fig. 4).
Step 3 Place the brackets on ends of the rails. Attach the brackets to the rails with a screw attached through back of bracket into each
internal screw boss (fig. 5).
Step 4 Prop rail in place and mark the bracket holes on both posts. Remove rail. Predrill screw locations through the posts, using a 3/16" drill
bit at top bracket locations and 9/64" drill bit at lower bracket locations.
Step 5 A rail support is needed every 2 feet (2 are included in the 6ft kit, 3 in the 8ft kit). Attach rail support connectors to the bottom of
the lower rail at 2-foot intervals. Predrill using a 1/8" drill bit. Attach the rail supports to the support block connectors. Mark the location of the
rail support on the deck surface and attach the other rail support connector to the deck using the included screw (fig. 7).
Step 6 Position the rail between the posts. Check for level end-to-end and vertically. Attach brackets to the post at one end. Repeat for the
other end. Note: Use a driver extension bit to avoid marring the rail with the drill chuck (fig. 6).
Step 7 Set post caps on each post. Gently tap with rubber mallet to secure.
Distance between posts
Subtract 0.5"
Subtract 0.5"
fig. 4
fig. 5
fig. 7
fig. 6
Stair Railing Installation Instructions
Prior to construction:
• Ensure post location is compatible with railing, prior to securing to the deck, place both posts in position, and lay the bottom rail along the
stair nosing from top to bottom adjacent to both posts. On the rail side of the post, measure up from the top of the rail and ensure there is a
minimum of 34" to the top of the post. Post location may need to be adjusted to ensure minimum is obtained. Repeat this step for the bottom
post.
• For a wood deck, position the post so the fasteners will go into the joists, and make sure the decking is firmly attached to the joists at the
location of the posts. Proper structural blocking/framing under the decking material is required when attaching the post to a wood frame deck
because decking alone is not approved as structural framing.
Step 1 Begin by determining where the top and bottom post will be located. Mark the desired location of the post.
Step 2 Four 3/8" diameter mounting holes are provided on the base. When final position is determined, mark hole locations and remove the
post assembly. Drill the marked locations through decking and into structural blocking.