FIREBOX INSTALLATION INSTRUCTIONS (CONT'D)
Locating Firebox
Pry the top standoffs up and bend pieces as shown. Attach
free-end to face top with two hex-head screws from hardware pack.
Place firebox in framing opening. Use the tabs on the side of the
firebox to attach firebox to framing. Different tab locations can be
used for finishing materials with thicknesses of 1/2 inch and 5/8 inch.
See Figure 9.
Framing tabs should fit directly against framing material. Use at
least one nail per bracket to secure in place.
Check squareness of the firebox prior to securing to framed opening.
See Figure 10.
FRAMING TABS
FRAMING HARDWARE
NOT INCLUDED
CHECK TO SEE
THAT BOX IS SQUARE
PRIOR TO ATTACHING TO
FIREBOX OPENING
Page 12
Figure 9
3/4" GAP
REQUIRED
FRAMING
Figure 10
Extended Hoods
If the non-combustible facing material used to finish the firebox is
over 1 inch thick, an extended hood that extends 2 inches farther into
the room is recommended. Contract your Empire Dealer for details.
VB4H32SS .............................Stainless Steel Extended Hood
VB4H36SS .............................Stainless Steel Extended Hood
VB4H42SS .............................Stainless Steel Extended Hood
Installing the Hood
A hood that is furnished with each firebox (or optional extension
hood) MUST be installed before the firebox is used. Failure to do
so may create a possible fire hazard.
1. Loosen the two screws (A) holding firebox top to face panel,
then slide the hood flange between the firebox top and face
panel and re-tighten the screws. See Figure 11.
2.
Install one screw at each end of the hood as shown (C). See
Figure 11.
Finishing
All joints (top, bottom and sides), where the wall or decorative
facing material meets the firebox surround must be sealed with a
non-combustible material (300°F + Sealant).
NOTICE: When installation application includes highly acidic
applications such as mortar or stone etching, do not remove
the protective PVC film from the stainless steel until after this
application is complete. Once the film has been removed we
recommend that the firebox be cleaned with a stainless steel
cleaner immediately.
Cleaning Instructions at Installation
This firebox is built using mostly high-grade stainless steel to
resist rust-through. In outdoor applications, all stainless steel will
develop a dull patina and, depending on the local environment
and on the materials used in the installation, may develop some
surface oxidation (rust). This does not affect the performance
of the firebox, and does not require any action to correct. If you
prefer keeping your firebox front looking factory-fresh, clean it as
required with stainless steel cleaner.
3/8" GAP
REQUIRED
C
A
Figure 11
C
A
44373-0-0522