Use 25~30 Kg dry cement and sand mix. Add water to
make a paste mortar. Remove the tub. Cover the
installation area with the mortar starting from the middle
of the tub as shown. The height of the mortar should
reach the bottom of the tub.
NOTE:
DO NOT CLOG THE DRAIN HOLE.
Place the tub onto the mortar. Insert the drain tailpiece
into the trap.
Make sure that the bottom of the tub is pressed into
mortar in order to secure the tub. Insert two wood
wedges under the tub to support the weight of the tub
until the mortar hardens. (Wedges will remain in the
mortar.) Frequently check the level of the tub.
25~30
B. Install Plumbing
CAUTION: Risk of damage to bath bottom and subfloor.
Ensure a watertight seal on the bath drain connections.
1)
. For through the floor drain installation, when the
bath is securely positioned, connect the drain to the
trap. See fig. A.
2). Install the faucet valving and spout tee. Open the
hot and cold water valves, and check the supply
connections for leaks.
3)
. Run water into the bath, and check the drain
connections for leaks.
B.
1).
2).