DRYER INSTALLATION

1. CODE CONFORMITY. All commercial dryer installations must conform with local codes or, in the absence of
local codes, with the latest edition of the National Fuel Gas Code ANSI Z223. 1. Canadian installations must comply
with current Standard CAN/CGA-B149 (.1 or .2) Installation Code for Gas Burning Appliances or Equipment, and local
codes if applicable. The appliance, when installed, must be electrically grounded in accordance with the latest edition
of the National Electric Code, ANSI/NFPA70, or, when installed in Canada, with Standard CSA C22.1 Canadian
Electrical Code Part 1.
2. INSTALLATION CLEARANCES: This unit may be installed at the following alcove clearance. (millimeters)
I.
Left Side
0"
II. Right Side 1"* (25)
III. Back
18" (457) (Certified for 1" (25) clearance; however, 18" (457) clearance is necessary behind the
belt guard to allow servicing and maintenance.)
IV. Front
48" (1220) (to allow use of dryer)
V. Top
Refer to figure labeled "Vertical Clearance Dimensions".
AB. Certification allows 0" clearance at the top 1" (25) back from the front. However, a 1/4" (6)
CD. A 4" (102) clearance is required at the top between 1" (25) and 4" (102) from front.
E. A 10" (254) clearance is required from top at all other points.
VI. Floor
This unit may be installed upon a combustible floor.
*Units may be installed in direct contact with an adjacent dryer, providing allowance is made for opening upper and
lower service doors.
Do not obstruct the flow of combustion and ventilation air.
Maintain minimum of 1" (25) clearance between duct and combustible material.
Refer to installation label attached to the inside surface of the upper door of the dryer for other installation
information.
clearance is required to allow opening the upper service door.