Anchor Installation: Core-Drill Retro-Fit
Bond at least one of the anchor inserts according to your
5.
local code requirements. For more information see NEC
Article 680.26.
Test fi t the anchor assembly into the pre-drilled holes and
6.
use a torpedo level to ensure your anchoring system is level.
SEE FIGURE 3
Remove the anchor assembly and fi ll each hole halfway
7.
with 2-part construction epoxy (or equivalent).
Place the anchor assembly back into the holes. Wiggle the
8.
assembly as it's reinserted to ensure the epoxy fully coats
the threads.
Once again, check that the anchor assembly is level and
9.
anchor inserts are fl ush with deck.
Once the epoxy has set up,
10.
remove the hardware and the
anchor jig plate. Your lift is now
ready to be mounted to the
anchoring system. The anchor jig
plate may be recycled or used to
install other anchors.
Copyright © 2019 Aqua Creek Products All Rights Reserved
*MIN AND MAX
SETBACK DISTANCES
ARE FOR TYPICAL
FLAT POOL DECK
APPLICATIONS. POOLS
WITH A RAISED CURB
OR IN GROUND SPAS
WITH BENCHES CAN
VARY. CHECK WITH
AQUA CREEK FOR
PROPER SETBACK
DISTANCES AND
ANCHOR LOCATIONS.
LIFT OUTLINE
FIGURE 3
(CONTINUED)
1/2" X 1-1/2" HEX BOLT (3)
1/2" FLAT WASHER (3)
ANCHOR
JIG-PLATE
P-7200ANB
ANCHOR INSERT (3)
*22 1/2" TO 38"
(4 3/4" MIN TO
17 3/4"
20 1/4" MAX SETBACK)
10"
CORE DRILL
4-1/2" DEEP, 3 PLACES
10"
USE JIG-PLATE
(LARGER HOLES)
USE JIG-PLATE
TO MARK LOCATIONS
ASSEMBLY FOR
TEST-FITTING AND
TO HOLD ANCHORS
IN PLACE AS EPOXY
CURES
Revised 6/18/19
FIGURE 2
SETBACK
1-1/2"
POOL WALL (OR
FURTHEST
OBSTRUCTION)
5