Dell PowerEdge 110 Посібник з монтажу - Сторінка 11
Переглянути онлайн або завантажити pdf Посібник з монтажу для Сервер Dell PowerEdge 110. Dell PowerEdge 110 32 сторінки. Dell poweredge 350 servers: installation guide
support.dell.com
Two-Post Flush-Mount Rack Kit Installation
This procedure provides instructions for installing a Dell system in a two-post open-
frame relay rack, such as those found in telecommunications equipment facilities.
Both 3-inch and 6-inch wide 2-post racks are accommodated.
The two-post open-frame relay rack must be properly secured to the floor, to the
ceiling or upper wall, and where applicable, to adjacent racks, using floor and wall
fasteners and bracing specified or approved by the rack manufacturer or by industry
standards. Refer to the two-post open-frame relay rack manufacturer's installation
documentation for precautionary warnings and information before attempting this
installation.
CAUTION: Do not attempt to install the system into a two-post open-frame
relay rack that has not been securely anchored in place. Damage to the
system and personal injury may result.
See "Safety Instructions" found earlier in this guide for additional safety information
regarding rack installation.
Rack Kit Contents
The two-post flush-mount rack kit includes the following items (see Figure 1-4):
•
Two flush-mount brackets
•
Two inner mounting rails
•
Four 12-24 x 0.5-inch pan-head Phillips (or slotted) screws
•
Four 10-24 x 0.25-inch flat-head slotted screws for securing the inner mounting
rails to the sides of the system
•
One 1-U template
Rack Installation Guide
1-5