2. CHECK LIST
In the event of unit failure and pre-commissioning checks to be made are determined as follows; after checking this information,
please contact our company in case failure continues.
Make sure that the unit receives power and electrical grounding is made!
Make sure that the electricity cables are drawn from in the correct cross section!
(Please check whether there is heating on cables or not.)
Please check whether the cables in unit control panel are shielded (shielded magnetic
field) or not; make sure shielding is grounded. If not, please change them!
Make sure that fresh air and exhaust air filters are clean and they do not block the
flow of air!
Please check whether the diameter of the air duct connection of the unit and the
diameter of the spigot are the same. If the duct connection is smaller, change it with
the correct one.
Make sure the electrical connections of the unit are made as suggested on the unit
and in this guide, check if there is incorrect connection.
Make sure during the installation of the unit there is enough space for the service and
if there is not enough space, re-install again.
After installing the unit, make sure that it does not create an abnormal sound or
vibration, if there is, make sure that rubber pads are used.
Controls