Galvin Engineering CliniMix 100.91.10.20 Installations-Manuale - Seite 3
Blättern Sie online oder laden Sie pdf Installations-Manuale für Temperaturregler Galvin Engineering CliniMix 100.91.10.20 herunter. Galvin Engineering CliniMix 100.91.10.20 4 Seiten. Bs lead safe thermostatic cartridge assembly for cmv2 low flow
Product Installation Guidelines
5. Remove cartridge
-
Use spanner size 28mm and turn the
cartridge in counterclockwise direction
until it reaches the end of its threads.
Pull the thermostatic cartridge out of
the mixer body. Open both (hot and
cold) water mains and check for leaks.
-
Open both isolating valves and check
for leaks.
Note: The flow might start from the inner part of the spout if the
main power remained on.
6. Assembly and testing
-
New cartridge can now be re-installed,
by screwing into the mixer body until it
reaches a firm stop. The cartridge
should be tightened to a torque of
15Nm. Re-install or install new plastic
lock supplied with the new cartridge.
© Galvin Engineering Pty Ltd
Version 1, 14 September 2022, Page 3 of 4
-
Remove the cartridge by hand
-
When service is complete, slowly turn the
cold-water isolation ball valve to 'OPEN'
position and inspect mixer body for leaks.
Repeat with hot water isolation ball valve.
-
Reassemble by reversing steps 1 and 2.
-
Re-commission the mixer as per
commissioning procedure (see units
installation instruction for details).