DataComm Cable Trench System CT-75-2P Hoja de instrucciones/instalación

Navegue en línea o descargue pdf Hoja de instrucciones/instalación para Electricidad industrial DataComm Cable Trench System CT-75-2P. DataComm Cable Trench System CT-75-2P 2 páginas.

Instruction / Installation Sheet
Cable Trench System
Part # CT-75-2P
Parts Included:
● (3) 15 in. Stackable Enclosure Box
● (1) 15 in. Stackable Enclosure Box w/ Open End Cap
● (1) 15 in. Stackable Enclosure Box w/ knockout End Cap
● (4) 15" Gangable Solid Cover
● (1) 15" Cover w/ Cable Pass-Through
Parts Identification:
A- (3) 15 in. Stackable Enclosure Box
B- (1) 15 in. Stackable Enclosure Box w/ Open End Cap
C- (1) 15 in. Stackable Enclosure Box w/ knockout End Cap
D- (4) 15 in. Gangable Solid Cover
E- (1) 15 in. Cover w/ Cable Pass-Through
F- (2) Screw Cover End Caps
G- (20) Screw Cover Screws
H- (36) Box Screws
Installation Instructions:
1. Preparing the Wall
Cut out a space in the dry wall 75in. tall (or increments of 15in.) x 15 in wide.
2. Placing the Bottom Box
Place the Stackable Enclosure Box w/ knockout End Cap (C) between studs where the cables are intended to exit the trench.
3. Installing the Bottom Box
Secure the two tabs to the studs using Metal Wood screws (not included) and a Phillips head Screwdriver.
Tools Needed:
● Phillips Head Screwdriver
● (10) Metal Wood Screws
F
G
D
E
F
Page 1 of 2
DataComm Electronics, Inc.
6349 Peachtree Street
Norcross, GA 30071-1725
888.223.7977
770.662.8205
www.DataCommElectronics.com
B
A
C
H
06/19/2018