GREEN BANK WG48350 Manual del usuario - Página 5

Navegue en línea o descargue pdf Manual del usuario para Batería GREEN BANK WG48350. GREEN BANK WG48350 7 páginas. Battery system for households

LiFePO4 Battery System for Households

3. INSTALLATION

3.1 Unpacking and Inspection

Before installation, please inspect the unit. Be sure that nothing inside the package is damaged. You
should have received the following items inside of package.
NO
NAME
SPECIFICATION
Grid activation communication wire
1
Communication line 1
( used with 6)
2
Used for Communication among batteries
Communication line 2
Used for communication between battery
3
Communication line 3
and host computer
4
Used for battery parallel connection
Cables
Used for activating the pack when grid
5
Adapter
power recover
Used for auto restart when PV comeback
6
PV Wake up line
in off-grid system
7
User manual
User manual
8
Guarantee card
Guarantee card

3.2 Mounting the Unit

Consider the following points before selecting where to install:
• Do not mount the battery on flammable construction materials.
• The ambient temperature should be between 0°C and 45°C to ensure optimal operation.
• The recommended installation position is to be adhered to the wall vertically.
• Be sure to keep other objects and surfaces as shown in the right diagram to guarantee sufficient heat dissipation and
to have enough space for removing wires.
Please follow below steps to implement battery connection:
1.Assemble battery ring terminal based on recommended battery cable and terminal size.
2.Connect all battery packs as units requires. It's suggested to connect at least 2 sets of WG48350 for
inverter larger than 6KVA in parallel connection.
Note: if you need the battery wake-up when the grid back, connect the battery with grid use
power adapter and communication line 1 shown in the package list.

3.3 Connection for Parallel Mode

The WG48350 series battery support to be connected in parallel for expansion. If you need one more battery
bank work in parallel mode, connect the battery as shown in PIC 1.
PICTURE
1
2
4
6
7
05
Main Circuit
3
5
Step 1: The schematic diagram of the parallel connection of three battery packs is shown in Figure 1.
Note:After completing the above steps, arbitrarily select the positive and negative poles of one of the battery packs to output.
After confirming the correct connection of the inverter, controller and battery, you can turn on any of the switches and
use the battery group happily.
For pure off grid system ,the PV awake wire need to be connected with MPPT charge controller if the battery
pack is charged by solar panels only . The connection diagram as below :
LiFePO4 Battery System for Households
06