Avlite AV-SIGN-20 Manuel d'installation et d'entretien - Page 9

Parcourez en ligne ou téléchargez le pdf Manuel d'installation et d'entretien pour {nom_de_la_catégorie} Avlite AV-SIGN-20. Avlite AV-SIGN-20 16 pages. Solar sign light

Regulator Connection Order
The label on the Regulator has each system connection labelled from 1 to 6. This is the recommended
order of system connections.
IMPORTANT: The BATTERY must be connected before the SOLAR to properly start the
microcontroller.
1. BATTERY: Connect the battery (+) and battery (-) to the Regulator
2. SOLAR: First, be certain the battery (+) and battery (-) is connected correctly. Then connect the
solar array to the SOLAR terminals.
Selecting Lighting Control Option
After completing the system connections, select the desired LIGHTING CONTROL option.
A brief description is as follows:
OFF
Lights remain turned off
2, 4, 6, 8, 10
Hours light is turned off after sundown
3/1, 4/2, 6/2
Light is turned on after sundown, turned off during the night, and turned on again
one hour (3/1) or two hours (4/2, 6/2) before sunrise
D/D
Dusk-to-Dawn, light is on all night
The factory setting of the light is D/D (Dusk-to-Dawn).
To select a lighting option, turn the rotary digital switch to the desired position. An arrow in the rotary
switch will point to the selected position. This is a digital switch, so it will click into each of the ten
positions.
To confirm correct selection of the desired control option, press the TEST button located below the
rotary switches.
SOLAR
4
3
+
Latest products and information available at www.avlite.com
Regulator Connection & Operation
CHARGING
TEMP SENSE
BATTERY
LIGHT
2
1
6
+
+
Regulator Diagram
LOW VOLTAGE
DISCONNECT
SEALED
5
OR
FLOODED
SELECT
9
AV-SIGN-20
Solar Sign Light
LIGHTING CONTROL
OFF
D/D
2
6/2
4/2
8
3/1
10
TEST
4
6