Application planning
4.1
Load cell dummies
Load cells are sensitive sensors. To protect the load cells from becoming damaged during
installation and transport, install the load cells only at the last minute. Replace the load cells
during installation and transport with placeholders, so-called dummies or phantoms.
4.2
Lifting protection
The following figure shows a proposed solution for lifting protection. The X designates the
possible lifting path of the load bearing implement. The bore ØD must be larger than the
diameter of the bolt Ød. The movement of the load bearing implement must not be hindered.
Figure 4-1
4.3
Load pick-up
Mounting surfaces
The following requirements apply to the installation areas:
● The positional and angular deviations of the mounting areas to each other correspond to the
general tolerances for welded constructions in EN ISO 13920.
● Ensure that the foundations are absolutely firm and free of depressions. Mount the
installation elements in concrete foundations on evenly cast steel plates.
● The mounting surfaces must be vertical to the measuring direction and preferably in one
plane.
● A plane of ≤ 0.2 mm is required for the mounting surfaces.
SB-S CA
Manual, 06/2019, A5E47600142-AA
Proposed solution for lifting protection
4
11