INTRODUCTION
Before any pelletizer can be installed, the owner/operator must prepare the site for installation and operation. It is the
owner's responsibility to verify all the necessary preparations have been made to the installation site and meet the
specifications and guidelines detailed in this publication. This may include but is not limited to:
Providing an indoor space with standard industrial flooring.
•
Installing a liquid CO
•
Installing a gaseous CO
•
Installing a power supply that is sufficient and up to code.
•
Providing proper room ventilation and other CO
•
Determine which options and other manufacturing accessories to add/prepare for maximizing production
•
performance and capabilities.
The owner is responsible for transmitting the specifications in this publication to other third-party contractors involved in
the pre-installation preparations of the site. Failure to properly prepare the site may delay the installation and/or optimal
performance of the pelletizer. The graphics used in this manual may show pelletizer details and installation components
that may be different than what is actually used. Components may have been removed for illustrative purposes or the
continuing improvement of the pelletizer's design may cause changes that are not included in this publication.
tank and supply pipeline system up to the connection point at the pelletizer.
2
exhaust pipeline from the pelletizer to free vent at a safe position.
2
Preinstallation manual
safety measures.
2
PE50 & PE80
Version:
1
Page:
4 of 15
Date:
22.02.2023