Dell PowerEdge 2650 Panduan Instalasi
F i g u r e 1 - 5 .
I n s t a l l a t i o n
shoulder washer
(2 per bracket)
mounting
flange
Holding the left slide assembly into position in the two-post rack at the location you
7
marked, adjust the extended back bracket tightly against the vertical two-post rack and
secure it with three 12-24 x 0.5-inch pan-head Phillips screws (see Figure 1-6).
Secure the front bracket on the slide assembly to the two-post rail with two
8
12-24 x 0.5- inch pan-head Phillips screws (see Figure 1-6).
Perform steps 7 and 8 to install the right slide assembly in the rack.
9
Use an 11/32-inch wrench or nut driver to fully tighten the nuts on the mounting
10
brackets on both slide assemblies that you tightened with your fingers.
Install the stiffening bracket between the slide assemblies and secure the bracket with
11
a 12-24 0.5-inch pan-head Phillips screw on each slide assembly (see Figure 1-6).
If the vertical rack is 3 inches wide, use the holes at the back end of the slide
assemblies (shown in Figure 1-6). If the vertical rack is 6 inches wide, use the holes
located 3 inches in front of the holes at the back end of the slide assemblies.
1-10
2-Pos t Rack Installation
R o t a t i n g t h e F r o n t M o u n t i n g B r a c k e t f o r F l u s h - M o u n t
nut (2 per bracket)
12-24 x 0.5-inch pan-head Phillips screws
(remove 2 per bracket)
NOTE: These screws are shown reinstalled on
the other slide assembly.