Step 1-2 : Press the 【F4 Setups】 key at the cutting interface→Into Parameter interface; →
Press the 【F2 Flame】; Need to change two parameter;
--Low Preheat Time
steel plate increases, the Preheat time increases.}
--Pierce 1 Time
of the steel plate increases, the Pierce time increases.}
Note: This time is based on the actual situation on site.
Step 2- Manual test flame cutting;{ We use oxygen+ acetylene as an example}
Step 2-1 : Connect acetylene and oxygen to the gas pipeline of the machine - red for gas pipeline
and blue for oxygen pipeline;
Unique Solution
100.00S{This is the Preheat time of the flame. As the thickness of the
01.50S{ This is the Pierce time of the flame cutting. As the thickness
Pic2
Change to 100S
Change to 01.50S