When commissioning KNX SUPERIO, the fol-
lowing steps must be followed:
˚ Power off the system/installation
˚ Install KNX SUPERIO on the installed moun-
ting unit
˚ Connect power supply and KNX bus to
KNX SUPERIO
˚ Power on the system/installation
˚ Wait until KNX SUPERIO has booted up
2.3.2 ENVIRONMENTAL CONDITIONS
The correct function of KNX SUPERIO can be granted only if the following requests are met:
OPERATION
2.3.3 COMMISSIONING
DIVUS KNX SUPERIO is power supplied by
230V AC
ATTENTION!
If the KNX SUPERIO hardware is
changed, irreversible damage can occur.
Any intervention on the equipment should
be performed only by authorized person-
nel of DIVUS.
Ambient temperature 0°C - 30°C
ATTENTION!
Before commissioning KNX SUPE-
For the usage/configuration of KNX-
SERVER a working network connection is re-
RIO all connections must be checked! Ve-
quired. In order to make the first access to
rify that the voltage of the connected po-
KNXSERVER, or if a compatible network is not
wer supply doesn't exceed the supported
available, follow these steps:
voltage range, in order to avoid damage
on the device!