3.2
In addition to the UAT3 kit, fiber or ribbon splice tray(s),
and cable closure or terminal, the following tools and materials are
required:
• Utility knife *
• Scissors*
• Fiber Clean® wipes *
• Vinyl tape *
• Cable ties *
• Spatula *
• Tape measure *
• Needle-nose pliers
• Model 45-163 for 0.125 - 0.218 in tubes (p/n 100107-01)
• Model 45-164 for 0.25 - 0.56 in tubes (p/n 3204002-01)
3.3
Additional items required for grounding:
• Grounding hardware and tools approved by your company
• Pliers
* Items available in the M67-003 Fusion Splicing Tool Kit
4.

Cable Preparation

4.1
Prepare the drop cable
according to instructions appropriate
for the cable and the closure or
terminal in which you are placing the
cables. Place the prepared drop cable
aside in a secure place.
4.2
Determine the center of the
slack loop of the cable. Measure and
mark a distance of 100 cm (40 in) on
both sides of this midpoint. Place a wrap of tape at each of these points
to mark a total of 200 cm (80 in) of cable to be accessed (Figure 3).
NOTE: More or less cable may be accessed according to slack need
and availability. This length could be 250 cm (100 in) or more.
When installing aerial terminals (such as the SCA), position the
terminal on the strand and then mark the appropriate section of
cable to be accessed.
Standard Recommended Procedure 004-074 | Issue 12 | May 2017 | Page 5 of 18
• Cotton swabs *
• Isopropyl alcohol
• Plastic bristle brush
(e.g., tooth brush)
• Permanent marking
pen *
• Ideal® buffer tube
cutters:
Tape
Figure 3