Wall mounting
The mounting location should be near an electrical outlet and within reach of the air inlet (the wall
mount flange or the intake blast valve). If the air intake hose will not reach the bottom air intake
port on the Safe Cell, 4 inch, schedule 40 ABS pipe and fittings should be used to connect the hose
to the air inlet. The air intake hose will slip fit onto a 4 inch pipe with an outer diameter of 4½
inches.
The Safe Cell needs to be mounted in a vertical position as shown below, unless a special carbon
adsorber is supplied that has internal baffles to mitigate the possibility of blowby if the carbon
settles. For ease of manual hand crank operation mount the Safe Cell to the wall with the bottom
sitting on the floor. The complete mounting system is first assembled on the Safe Cell so that the
fastener holes can be located on the wall. One end detail is shown below, the other end mounting
arrangement is identical:
1. Assemble the clamp bars (item 5, below) to the Safe Cell by inserting them between the
top and bottom end bell flanges and sliding the threaded rod (item 1, below) through the
tubes and threading on the flange nuts (item 2, below).
2. Assemble the wall mount brackets (item 3, below) to the clamp bars (item 5, below) and
tighten down the star nuts (item 6 below) .
3. Put the Safe Cell in place on the floor with the wall mount brackets up against the wall.
4. Locate and mark the center of the hole locations for the wedge anchors (item 4, below).
5. Remove the Safe Cell. Drill the holes and install the wedge anchors. See page 19 for wedge
anchor instructions.
6. Remove the wall mount brackets from the clamp bars and assemble them onto the wedge
anchors and tighten the nuts.
7. Assemble the Safe Cell to the wall mount brackets and tighten the star nuts.
Figure D-1