Site Preparation
This chapter describes requirements and site setup procedures for your S2410 system.
This chapter covers the following topics:
•
Site Selection
•
Cabinet Placement on page 11
•
Rack Mounting on page 12
•
Fans and Airflow on page 12
•
Power on page 12
•
Storing Components on page 12
•
Tools Required on page 13
For detailed S2410 specifications, refer to
NOTE: Install the S2410 into a rack or cabinet before installing any optional components.
Site Selection
Make sure that the area where you install your S2410 chassis meets the following safety requirements:
• Near an adequate power source. Connect the system to the appropriate branch circuit protection as
defined by your local electrical codes. Ideally, you connect each power supply to a separate circuit.
• Environmental temperature between 32° – 122°F (0° – 40°C).
• Relative humidity that does not exceed 90% non-condensing.
• In a dry, clean, well-ventilated and temperature-controlled room, away from heat sources such as hot air
vents or direct sunlight.
• Away from sources of severe electromagnetic noise.
• Positioned in a rack, cabinet, or on a desktop with adequate space in the front, rear, and sides of the unit
for proper ventilation, and access (see below).
Cabinet Placement
The cabinet must meet the following criteria:
• Minimum cabinet size and airflow are according to the EIA standard.
• Minimum of 5 inches (12.7 cm) between the side intake and exhaust vents and the cabinet wall.
Chapter , S2410 Specifications, on page