- ページ 9
溶接アクセサリー Miller Travel Master SB-10DのPDF オーナーズマニュアルをオンラインで閲覧またはダウンロードできます。Miller Travel Master SB-10D 44 ページ。 Automatic welding sidebeam
9.
Install supplied pinion gear guard onto bottom
side of motor casing.
10.
Adjust position of front two cam rollers on car-
riage as follows:
IMPORTANT: All directions, such as left or right, are
with respect to the operator facing the carriage.
a. Be sure that a safety stop is installed onto each
end of beam.
b. Roll carriage to right end of beam.
c. Using a 1/4 in. (6.4 mm) Allen wrench, rotate
cam adjustment on underside of right, front cam
follower until cam is as close to beam bearing
bar as possible without touching it.
d. Tighten nut on top side of cam follower.
e. Roll carriage to left end of beam, and adjust po-
sition of left, front cam follower according to
Steps 10c and d.
11.
Install motor release lever onto either side of mo-
tor casing with lever extending out over carriage.
Secure lever to motor using supplied 5/16-18 but-
ton-head socket capscrews.
3-5.
CARRIAGE CONTROL METER DISPLAY SE-
LECTION PROCEDURE
WARNING: ELECTRIC SHOCK can kill.
Do not touch live electrical parts.
Shut down Carriage Control and welding
power source, and disconnect input power
employing lockout/tagging procedures be-
fore inspecting, installing, or adjusting.
Lockout/tagging procedures consist of remov-
ing input plug from receptacle, padlocking line
disconnect switch in open position, removing
fuses from fuse box, or shutting off and red-tag-
ging circuit breaker or other disconnecting de-
vice.
CAUTION: ELECTROSTATIC DISCHARGE
(ESD) can damage circuit board compo-
nents.
Put on properly grounded wrist strap
BEFORE handling circuit boards.
Transport all static-sensitive components in
proper static-shielding carriers or packages.
Perform work only at static-safe work area.
The digital meter is capable of reading the travel or jog
speed in inches per minute (ipm) or meters per minute
(mpm). The unit is shipped with the meter set to display
the speed in ipm. To change the meter display, proceed
as follows:
1.
If applicable, remove the four screws securing
the Carriage Control to the mounting bracket,
and remove the control from the bracket.
2.
Remove the securing screws from control wrap-
per, and remove wrapper.
3.
Locate Meter Selection Switch on Timer Board
PC2 (PC2 is located on the base panel in the con-
trol). Place Selection switch in desired position
(IPM or MPM).
4.
Reinstall and secure control wrapper.
5.
Reposition and secure control onto control
mounting bracket.
3-6.
CARRIAGE CONTROL INSTALLATION (Fig-
ure 3-1)
1.
Install and secure end cap onto crossarm.
2.
Install and secure crossarm onto front face of car-
riage using supplied 3/8-16 x 1-1/2 in. hardware.
(Three mounting positions are available. Refer to
Figure 3-1.)
IMPORTANT: The crossarm may be shortened. Cut
crossarm to desired length.
3.
Install Carriage Control mounting bracket to
either side of crossarm, and secure bracket using
supplied 3/8-16 x 1 in. hardware.
4.
Remove base mounting screws in Carriage Con-
trol, and install control onto mounting bracket,
aligning mounting screws with holes in mounting
bracket.
5.
Reinstall base mounting screws.
3-7.
SPOOL SUPPORT ASSEMBLY INSTALLA-
TION (Figure 3-1)
1.
Slip the riser clamp over the spool mount riser.
2.
Install and secure riser assembly onto top of car-
riage using supplied 3/8-16 x 1-1/2 in. hex-head
capscrews and associated hardware.
3.
Install spool mounting arm onto riser, aligning
mounting holes in arm with desired holes in riser.
Secure arm using supplied 1/2-13 x 3-1/2 in. hex-
head capscrews and associated hardware.
4.
Install the hub assembly onto the spool mounting
arm as follows:
a. Remove hex nut from end of hub support shaft.
b. Install the hub support shaft through the desired
mounting hole in the mounting arm.
c. Reinstall and secure hex nut onto end of sup-
port shaft.
OM-889 Page 5