Commissioning
Before closing the electrical panel and leaving
the site, make sure to properly commission the
installation. Verify the following:
•
Phasing: Verify CTs are on the correct
phases. A handheld voltmeter can be
used to check, for example, the meter's L1
voltage terminal is the same phase as the
breaker that the CT port 1 is measuring.
See the following page for more
information on phasing.
•
All CTs are facing the correct direction
and fully latched.
•
Network connectivity on the eGauge LCD
screen.
•
Network connectivity with a new browser
window.
•
Software configuration is correct in
Settings → Installation.
Use the Channel Checker (Tools →
•
Channel Checker) to verify voltage,
amperage, and power readings.
11