eGauge EG4 Series Посібник із швидкого старту - Сторінка 11
Переглянути онлайн або завантажити pdf Посібник із швидкого старту для Вимірювальні прилади eGauge EG4 Series. eGauge EG4 Series 12 сторінок.
Commissioning
Before closing the electrical panel and leaving
the site, make sure to properly commission the
installation. Verify the following:
•
Phasing: Verify CTs are on the correct
phases. A handheld voltmeter can be
used to check, for example, the meter's L1
voltage terminal is the same phase as the
breaker that the CT port 1 is measuring.
See the following page for more
information on phasing.
•
All CTs are facing the correct direction
and fully latched.
•
Network connectivity on the eGauge LCD
screen.
•
Network connectivity with a new browser
window.
•
Software configuration is correct in
Settings → Installation.
Use the Channel Checker (Tools →
•
Channel Checker) to verify voltage,
amperage, and power readings.
11