Ridge Insert Weldment
SIDE VIEW
Step 1
The liner will be hoisted by ropes attaching to
eyenuts that are attached to the peak weldment
upright location as shown in Figure 1.
It will be easier to install these bolts and eyenuts
if it is done before the frame is raised or the
fabric is installed. Place one eyenut at each
peak weldment with all eyenuts facing the same
direction except at (1) end.
Step 2
Lay out liner pieces on drop cloths in their
respective placements. Check the pieces to
be sure velcros go together correctly and the
good side of the liner faces the ground. Please
note that gable ends are built into adjacent mid
pieces.
2
Ridge Insert Weldment
upright bracket
Liner
FRONT VIEW
Bolt with eyenut thru
peak weldment upright
location.
Carabiner
Block
Liner
Figure 1
Ridge Insert Weldment
Figure 2