Anchor Venue Series 설치 지침 매뉴얼 - 페이지 2

{카테고리_이름} Anchor Venue Series에 대한 설치 지침 매뉴얼을 온라인으로 검색하거나 PDF를 다운로드하세요. Anchor Venue Series 8 페이지. Structures
Anchor Venue Series에 대해서도 마찬가지입니다: 설치 지침 매뉴얼 (7 페이지)

Ridge Insert Weldment

SIDE VIEW

Step 1
The liner will be hoisted by ropes attaching to
eyenuts that are attached to the peak weldment
upright location as shown in Figure 1.
It will be easier to install these bolts and eyenuts
if it is done before the frame is raised or the
fabric is installed. Place one eyenut at each
peak weldment with all eyenuts facing the same
direction except at (1) end.
Step 2
Lay out liner pieces on drop cloths in their
respective placements. Check the pieces to
be sure velcros go together correctly and the
good side of the liner faces the ground. Please
note that gable ends are built into adjacent mid
pieces.
2
Ridge Insert Weldment
upright bracket
Liner

FRONT VIEW

Bolt with eyenut thru
peak weldment upright
location.
Carabiner
Block
Liner
Figure 1
Ridge Insert Weldment
Figure 2