After the bottom duct work is positioned in place,
remove the three T25 screws from the outer holes in
the mounting brackets on the sides and front of the
duct work and move them to the inner holes of the
same brackets. Tighten the three screws to the
specified torque.
The bottom duct work is not fastened to the enclo-
sure.
Install the front cover of the duct and the cable
clamp bracket if used. Install the two remaining
gland plates.
Note: The cable clamp bracket is grounded
through the screws that secure the bracket to
the duct. If additional grounding is desired the
grounding strap that is supplied with the kit may
be installed.