Danfoss VLT 6000 series Інструкція з експлуатації - Сторінка 10

Переглянути онлайн або завантажити pdf Інструкція з експлуатації для Конвертер мультимедіа Danfoss VLT 6000 series. Danfoss VLT 6000 series 16 сторінок.

Danfoss VLT 6000 series Інструкція з експлуатації
After the bottom duct work is positioned in place,
remove the three T25 screws from the outer holes in
the mounting brackets on the sides and front of the
duct work and move them to the inner holes of the
same brackets. Tighten the three screws to the
specified torque.
The bottom duct work is not fastened to the enclo-
sure.
Install the front cover of the duct and the cable
clamp bracket if used. Install the two remaining
gland plates.
Note: The cable clamp bracket is grounded
through the screws that secure the bracket to
the duct. If additional grounding is desired the
grounding strap that is supplied with the kit may
be installed.
Instruction No: 175R5640 V3
Aug 13, 2008
Page 10
Outer hole
Photo 28. Move mounting screws
from the outer hole to the inner hole
Photo 29. Installed ductwork
Inner hole