The required depth of the
pad will vary from site to
site. Normally, the pad
should be at least 4" above
the surface and 18" below
(Figure A & B).
In harder soil or rock, pilings may be preferred (Figure C).
Conduit requirements should be considered in the planning stage. If electrical power is required, a separate conduit should be
installed for electrical only. A certified electrician should be consulted for the proper conduit material (Figure D & E).

PAD INSTALLATION

Driveway
5"
Fig. D
Direction of Opening
5"
24"
12"
24"
Pad Location
Pad Location
Fig. A
14"
AREA FOR CONDUIT
ENTRY
6
Fig. B
Fig. C
Note:
Allow the
concrete to cure
3"
as per the
directions on the
bag. The
mounting holes
for the operator
should be drilled
after the concrete
has cured.