Product Installation Guidelines
INSTALLATION
INSTALLATION COMPLIANCE: Galvin Engineering products must be installed in accordance with these
installation instructions and in accordance with AS/NZS 3500, the PCA and your local regulatory requirements.
Water and/or electrical supply conditions must also comply to the applicable national and/or state standards.
Failing to comply with these provisions shall void the product warranty and may affect the performance of the
product.
1. Fit tap assembly
Fit the tap as shown above.
When applying thread tape or sealant to the inlet, ensure the opening is not obscured. Failure to do so
may restrict or block the flow restrictor, affecting the flow of water.
Blanking Screw
2. Flow adjustment
 To adjust water flow
1. Remove the blanking screw
2. Adjust the water flow by turning the
regulator screw. Test both the bubbler
water height and bottle filler flow.
3. Replace blanking screw
Note: The full range from minimum flow to
maximum flow is only ¼ turn
© Galvin Engineering Pty Ltd
Regulating Screw
3. Testing
Version 1, 13
Once the drinking tap has been installed,
test for leaks and correct operation.
th
June 2023, Page 3 of 4