Preparation (cont.)
NOTE: The supply stop handles can not extend more than 4-3/4"
(12.1 cm) from the finished wall when in the fully open position.
Install the water supplies and drain piping according to the
roughing-in information. Install the supply stops so the handles
will not touch the pedestal when fully open.
Install sufficient backing behind the finished wall to provide a
secure material for the anchoring devices.
NOTE: Ensure that the hanger is level and is secured to the backing
material behind the finished wall.
NOTE: Ensure that the spring clips are between the hanger and the
finished wall before tightening.
Using 1/4" (6 mm) lag bolts or equivalent (not provided), install
the hanger, spring clips, and angle bracket to the wall according
to the roughing-in information.
Carefully lift the lavatory into place on the hanger, and level. You
may need to raise or lower the hanger so the lavatory contacts
the wall evenly.
NOTE: The lavatory must be supported by the hanger.
Locate the two lavatory anchoring holes, and mark the hole
locations on the finished wall.
Carefully remove the lavatory from the area.