Allied Systems LONG REACH CCHA 설치 유지보수 및 서비스 매뉴얼 - 페이지 13

{카테고리_이름} Allied Systems LONG REACH CCHA에 대한 설치 유지보수 및 서비스 매뉴얼을 온라인으로 검색하거나 PDF를 다운로드하세요. Allied Systems LONG REACH CCHA 19 페이지. Carton clamp with load stabilizer

Shim(s)
as required
Figure 4-1, Lower Hook Clearance
9. Check all fittings, connections and bolts for any
interference.

4.5 Hydraulic Connections

1. Prior to connecting the truck hydraulic system to the
attachment, the system must be purged through the
filtration system. This will eliminate any contamina-
tion that might exist in the auxiliary hydraulic system
of the truck.
2. Purging can be accomplished by installing a jumper
line and operating each hydraulic function (clamp,
rotate and side shift if equipped) in each direc-
tion for a minimum of 30 seconds. (Figure 4-2)
Hoses should meet or exceed SAE100 RI Type AT,
with maximum working pressure of 3,000 psi for all
attachment functions.
45-034, REV. 5/18
Maximum
clearance
3/32"
Shim(s)
as required
Maximum
clearance
1/32"
Maximum
clearance
1/8"
(consult factory
if over)
To Truck
Figure 4-2, Jumper Line
3. Install the lines from the truck's hydraulics to the
hydraulics of the attachment.
Figure 4-3, Hydraulic Connection
4. Inspect installation to ensure hoses are not kinked or
pinched between the truck carriage and attachment.
5. Operate the attachment continuously for several
minutes to determine that all hydraulic connections
are secure with no leaks.
6. With the mast in the vertical position, rotate the
attachment fully 360°. After this procedure, check
that the truck's hydraulic reservoir oil level is at the
recommended level.
7. Before placing the attachment in operation inspect
all hoses and fittings for leaks and routing clearance.
Be sure to include clearance of jumper hoses to the
mast.
6. After completing the installation, operate the attach-
ment without a load for several cycles to remove
any air in the hydraulic system. Test the attachment
with a load to make sure the attachment operates
correctly.
To Clamp
13