Cisco 2300 설치 참고 사항 - 페이지 10
{카테고리_이름} Cisco 2300에 대한 설치 참고 사항을 온라인으로 검색하거나 PDF를 다운로드하세요. Cisco 2300 20 페이지. Switches and power supply modules
Power Supply Module Installation
Use the ground screw to attach the single-ground lug and wire assembly or the dual-ground adaptor to
Step 5
the switch rear panel. Using a ratcheting torque screwdriver, torque the ground-lug screw to 60 lbf-in.
(960 ozf-in.)
For a dual-ground adaptor, attach the dual-hole lug and wire assembly to the adaptor with the supplied
Step 6
nuts
Figure 10
1
2
Connect the other end of the grounding wire to an appropriate grounding point at your site or to the rack.
Step 7
Installing the DC Power Supply in the Switch
To remove and install a DC-powered power supply module, follow these steps:
Turn off power at the DC circuits. To ensure that power is removed from the DC circuits, locate the
Step 1
circuit breakers for the DC circuits, switch the circuit breakers to the OFF position, and tape the
circuit-breaker switches in the OFF position.
Use a number-2 Phillips screwdriver to remove the plastic safety cover from the power supply terminal
Step 2
blocks.
Use a number-1 Phillips screwdriver to remove the DC-input power wires from the power terminals.
Step 3
Installation Notes for Catalyst 3750-E, Catalyst 3560-E Switches and RPS 2300 Power Supply Modules
10
(Figure
10).
(Figure
10).
Attaching the Ground Lug and Wire Assembly
1
Single-ground screw and lug ring
Dual-ground adaptor and dual-hole lug
2
F R
F
78-17570-01