Power Supply Module Installation
Use the ground screw to attach the single-ground lug and wire assembly or the dual-ground adaptor to
Step 5
the switch rear panel. Using a ratcheting torque screwdriver, torque the ground-lug screw to 60 lbf-in.
(960 ozf-in.)
For a dual-ground adaptor, attach the dual-hole lug and wire assembly to the adaptor with the supplied
Step 6
nuts
Figure 10
1
2
Connect the other end of the grounding wire to an appropriate grounding point at your site or to the rack.
Step 7
Installing the DC Power Supply in the Switch
To remove and install a DC-powered power supply module, follow these steps:
Turn off power at the DC circuits. To ensure that power is removed from the DC circuits, locate the
Step 1
circuit breakers for the DC circuits, switch the circuit breakers to the OFF position, and tape the
circuit-breaker switches in the OFF position.
Use a number-2 Phillips screwdriver to remove the plastic safety cover from the power supply terminal
Step 2
blocks.
Use a number-1 Phillips screwdriver to remove the DC-input power wires from the power terminals.
Step 3
Installation Notes for Catalyst 3750-E, Catalyst 3560-E Switches and RPS 2300 Power Supply Modules
10
(Figure
10).
(Figure
10).
Attaching the Ground Lug and Wire Assembly
1
Single-ground screw and lug ring
Dual-ground adaptor and dual-hole lug
2
F R
F
78-17570-01