TSU-M
1
GENERAL INFORMATION
About engineering and application practices
This bulletin only refers to the assembly of the unit. To ensure a proper operation, a correct integration of the unit in
the overall installation is mandatory. For good engineering and application practices on layout, levelling,
connecting pipework, etc., please refer to our website: http://www.baltimoreaircoil.eu/knowledge-
center/application-information.
Shipping
BAC equipment is factory assembled to assure uniform quality and minimum field assembly.
For the dimensions and weights of a specific unit or section, refer to the certified drawing.
Before final placement of the thermal storage unit, remove the shipping skids, as illustrated in below figures.
Removal of shipping skids – Side view & End view
Remove these screws to unfasten shipping skid. Re-install screws where necessary.
Inspection Before Rigging
When the unit is delivered to the jobsite, it should be checked thoroughly to ensure all required items have been
received and are free of any shipping damage prior to signing the bill of lading.
The following parts should be inspected:
•
Exterior panels and covers
•
Ice coils
•
Sight tube and Ice Logic ice quantity controller (optional)
If shipping damage has occurred, this should be clearly indicated on the CMR.