ALUZ ZIBI A1 Series Installation Instructions Manual - Page 5
Browse online or download pdf Installation Instructions Manual for Lighting Equipment ALUZ ZIBI A1 Series. ALUZ ZIBI A1 Series 11 pages. Surface zuco pivot bios illuminated
Also for ALUZ ZIBI A1 Series: Installation Instructions Manual (12 pages), Manual (11 pages), Manual (13 pages), Manual (11 pages)
DRY LOCATION APPLICATIONS
1
Measure area where luminaire will be installed. Use a laser line to
create a reference line along installation area, ensuring consistent
alignment of mounting clips. Mark location where each mounting
clip will be installed along reference line.
2
Use 1 mounting clip every 2', rounded up. Use a minimum of 2
mounting clips per fi xture segment. For vertical applications, create
a stopper at the bottom of the run to prevent sliding.
3
Use a mounting clip at the junction between two fi xture segments.
Example: 20' Run.
4
Lay mounting clips along reference line and pre-drill using an
appropriate drill bit for surface material and screw size.
Typical screw size is 8/32 x 1".
Note: Allow 1/4" clearance on each side of mounting clip due to
lateral expansion. Only install mounting clips on flat, even surfaces.
5
Screw mounting clips to surface, then snap fi xture into mounting clips.
a
Screw MC to surface, then snap luminaire into mounting clips.
b
Screw MC-2 to surface, then snap luminaire into mounting clips.
c
Screw MC-3 to surface, then snap luminaire into mounting clips.
d
Screw MC-4 to surface, then snap luminaire into mounting clips.
1170 N Red Gum St, Anaheim, CA 92806
aluz.lighting
© ALUZ All Rights Reserved. ALUZ reserves the right to make changes or withdraw specifi cations without prior notice.
A1 Series | Surface
ZUCO Standard BIOS Illuminated
(A1-ZUCO-STN-BIOS)
866.ALUZ.LTG | 714.535.7900
WET LOCATION APPLICATIONS
1
Measure area where luminaire will be installed. Use a laser line to
create a reference line along installation area, ensuring consistent
alignment of mounting clips. Mark location where each mounting
clip will be installed along reference line.
2
Use 1 mounting clip every 2', rounded up. Use a minimum of 2
mounting clips per fi xture segment. For vertical applications, create
a stopper at the bottom of the run to prevent sliding.
3
Space mounting clips evenly throughout the run.
Example: 20' Run.
e
Screw MC-ADJ to surface, then snap luminaire into mounting clips.
f
Snap luminaire into magnetic clips, then attach to metal surface.
See Next Page for
Assembled Dimensions
Page 5 of 11
Mounting Clips
Installation Instructions
8 / 9 / 2023 / Rev 0