DRY LOCATION APPLICATIONS
1
Measure area where luminaire will be installed. Use a laser line to
create a reference line along installation area, ensuring consistent
alignment of mounting clips. Mark location where each mounting
clip will be installed along reference line.
2
Use 1 mounting clip every 2', rounded up. Use a minimum of 2
mounting clips per fi xture segment. For vertical applications, create
a stopper at the bottom of the run to prevent sliding.
3
Use a mounting clip at the junction between two fi xture segments.
Example: 20' Run.
4
Lay mounting clips along reference line and pre-drill using an
appropriate drill bit for surface material and screw size.
Typical screw size is 8/32 x 1".
Note: Allow 1/4" clearance on each side of mounting clip due to
lateral expansion. Only install mounting clips on flat, even surfaces.
5
Screw mounting clips to surface, then snap fi xture into mounting clips.
a
Screw MC to surface, then snap luminaire into mounting clips.
b
Screw MC-2 to surface, then snap luminaire into mounting clips.
c
Screw MC-3 to surface, then snap luminaire into mounting clips.
d
Screw MC-4 to surface, then snap luminaire into mounting clips.
1170 N Red Gum St, Anaheim, CA 92806
aluz.lighting
© ALUZ All Rights Reserved. ALUZ reserves the right to make changes or withdraw specifi cations without prior notice.
A1 Series | Surface
ZUCO Standard BIOS Illuminated
(A1-ZUCO-STN-BIOS)
866.ALUZ.LTG | 714.535.7900
WET LOCATION APPLICATIONS
1
Measure area where luminaire will be installed. Use a laser line to
create a reference line along installation area, ensuring consistent
alignment of mounting clips. Mark location where each mounting
clip will be installed along reference line.
2
Use 1 mounting clip every 2', rounded up. Use a minimum of 2
mounting clips per fi xture segment. For vertical applications, create
a stopper at the bottom of the run to prevent sliding.
3
Space mounting clips evenly throughout the run.
Example: 20' Run.
e
Screw MC-ADJ to surface, then snap luminaire into mounting clips.
f
Snap luminaire into magnetic clips, then attach to metal surface.
See Next Page for
Assembled Dimensions
Page 5 of 11
Mounting Clips
Installation Instructions
8 / 9 / 2023 / Rev 0