DROTSKY Engineering M100 Gebruikershandleiding - Pagina 6
Blader online of download pdf Gebruikershandleiding voor {categorie_naam} DROTSKY Engineering M100. DROTSKY Engineering M100 6 pagina's. Hammer mill
3. START AND USE
Prior to start-up
Inspect the hammer mill for any damages that could have occurred
during transport. For hydraulically driven models ensure that all hy-
draulic fittings and piping are connected and tightened. There are only
two pipes that need to be connected during assembly. The pressure
and return line. Check hydraulic tank level.
Check the machine for any loosened bolts and nuts
Remove lifting lugs from the bale conveyor. Position indicated above
by the yellow outlined triangle. Adjust the conveyor feet onto the floor
and lock in position. These should be adjusted so that the conveyor
front and back are level. These are positioned upward when opening
the door. Shown above within the yellow rectangle. Remove any for-
eign materials from the conveyor belt. Remove any foreign material
form the hammer mill chamber.( This includes the spare screen). Turn
the bale shredder by hand to ensure no collision is prominent.