Dell S4100-ON Series Installatiehandleiding - Pagina 9

Blader online of download pdf Installatiehandleiding voor {categorie_naam} Dell S4100-ON Series. Dell S4100-ON Series 21 pagina's.
Ook voor Dell S4100-ON Series: Installatiehandleiding (47 pagina's), Installatiehandleiding (48 pagina's), Installatiehandleiding (49 pagina's)

Dell S4100-ON Series Installatiehandleiding
To install the S4100–ON Series, Dell recommends completing the installation procedures in the order presented in this section.
Always handle the S4100–ON Series switch and its components with care. Avoid dropping the system or any field replaceable units (FRUs).
NOTE:
ESD damage can occur if components are mishandled. Always wear an ESD-preventive wrist or heel ground strap when
handling the S4100–ON Series switch and its components. As with all electrical devices of this type, take all the necessary safety
precautions to prevent injury when installing this system.
NOTE:
For more information, see the
Topics:

Unpack the system

Unpack
Rack or cabinet installation
ReadyRails installation
1U Tool-less mount installation
Two-post flush-mount installation
Two-post center-mount installation
Four-post threaded installation
S4100-ON Series system installation
1U front-rack installation
Optics installation
Optics removal
System power-up
After system installation
Unpack the system
NOTE:
Before unpacking the system, inspect the container and immediately report any evidence of damage.
When unpacking the S4100–ON Series switch, make sure that the following items are included:
One S4100–ON Series switch
One RJ-45 to DB-9 female cable
Two sets of rail kits, no tools required
Two PSUs
Three or four fan units
Two country- and region-specific AC power cords
Dell Networking S4100–ON Series Setup Guide
Safety and Regulatory Information
Warranty and Support Information
S4100–ON Series installation
Open Networking Hardware Diagnostic Guide .
S4100–ON Series installation
3
9