7. Attach leveling feet to bottom locker base frame
• Base frame should have one (x1) adjustable leveling foot per corner. Base frame may come with these
already installed
• If base frame does not have adjustable leveling feet installed, screw in one foot per corner of frame.
Feet to be screwed in from bottom of frame
• Try to use an install location where ground is already as flat and as unobstructed as possible (areas
without bumps, dips, raised sections from roots or ground features).
• Ground type should be solid eg.: concrete, asphalt, bitumen etc.
• Level base frame by raising/ lowering corners by screwing adjustable feet in and out.
• Feet have a limited range of travel and may not accommodate all surfaces, levels or gradients
• Use spirit-level placed on top of frame, to assist in getting frame as level as possible.
NOTE: Ensure all feet contact with ground firmly after leveling, frame cannot rock or lean at any corner,
or when fastened with anchor bolts, frame will be warped and not level and will effect assembly of locker.