3.3 Supply Connection
The supply cable routing must be proper. Ensure the sufficient supply cable sizes in the instal-
lation. No additional loads in the same supply line.
See figure 2.
•
Pull the supply cable through the cable lead through plate 350mm - 400mm measured
from the lead through.
•
Remove the sheath of the supply cable at the length of max. 250mm.
•
Cut the leads in different lengths so that the PE cable is the longest and strip them at the
length of 23mm.
•
Connect the supply cable leads to the supply connectors according to the connection dia-
gram. Ensure strain relief to the cables by fastening it on the cable support that is located
under the supply connectors.
IMPORTANT NOTICE: eFiller needs to be installed to a dedicated supply line, which is equipped
with 30mA residual current device (RCD-B) and 16A circuit breaker (MCB).