Liquid CO
Degasser System
2
In order to achieve a consistent, high-quality supply of liquid CO
an automatic gas venting system, such as the Armstrong Kit.
Installing an automatic gas venting system will improve the performance of the pelletizer and increase dry ice production.
The installation of the Armstrong Kit, or similar system, is optional and is the responsibility of the installer of the liquid CO
supply system and piping up to the pelletizer connection.
Gas CO
Exhaust System
2
An exhaust pipeline with an internal diameter greater than 25,4 mm (1 inch) is installed to facilitate the exhaust CO
from the dry ice production process. The exhaust CO
weatherproof outlet that prevents rainwater or other contaminants from blocking or creating back-pressure to the
pelletizer.
Additionally, the CO
exhaust could have a temperature as low as -27°C (-16.6°F) which may generate condensation. Cold
2
Jet recommends installing an Armaflex insulation or similar product to prevent this condensation from dripping down onto
the machine or production room floor.
to the pelletizer, Cold Jet recommends the installation of
2
gas must be vented at a safe location outside of the building with a
2