Green Brook Phoenix ELLEDH2 Руководство по установке и эксплуатации - Страница 3

Просмотреть онлайн или скачать pdf Руководство по установке и эксплуатации для Осветительное оборудование Green Brook Phoenix ELLEDH2. Green Brook Phoenix ELLEDH2 6 страниц. Led 4 in 1 hanging sign light

Wall
Wiring Diagram
(L) Switched Live -
Terminal (L1):
Terminal (L):
Terminal (E):
Terminal (N):
Warning: Failure to comply with these installation instructions may result in irreparable damage to the
main circuit.
1.
Restore the power supply.
2.
The LED indicators should light to indicate correct charging.
Normal Fitting: Green Indicator working
3.
The use of the 'Test' Button
When the TEST button is pressed and held in the product will go into emergency mode. When TEST
button is released product will return to normal operation.
Allow a brief time for initial partial charging and then isolate the permanent live supply by removing the
fuse from the fused spur box. Check to ensure the lamp is then illuminated from the battery cell pack
supply.
After a further 24 hours on a continuous charge, and only at a safe and appropriate time, mains
failure should be simulated to ensure that full duration rating is achieved. Thereafter the re-charge
time is 24 hours.
Flagpole

WIRING INSTALLATION

Brown
(L)Permanent Live -
On this unit continuous illumination is provided by a link connected between the
L1 and L terminal, this can be replaced by a switch for on/off control. Remove
link for non-maintained operation, switched live connection not required for
non-maintained operation.
This is the live supply to the charging circuit and must be permanent and
unswitched.
This is for maintaining the electrical continuity of an earthed conductor
when necessary (looping-in).
This is the neutral supply and must be permanent.
DO NOT HIGH-VOLTAGE TEST THIS UNIT, OR THE LIGHTING
SYSTEM WITH THIS UNIT CONNECTED.
COMMISSIONING & TESTING
Wall
Dia.3.
(E)Earth -
Green/Yellow
Brown
Unit Failure: Green indicator turned off
Wall Mounted
Dia.4.
(N)Neutral