6. Pre-fit the Shower Walls Together
NOTE: The module must be plumb and level. The shower door will not install properly if the module is not
plumb and level.
- Carefully move the wall assembly onto the receptor.
- Align the receptor and the walls.
- Check and align the walls for plumb and level.
- If walls are not plumb and level, go to section 7, "Shimming Procedures".
- Predrill the nail- in flanges on the stud centers and around the walls on 8" (20.3cm) centers. Do not nail the walls
in place at this time.
Kohler Co.
Align these two surfaces
on both walls
8" (20.3cm)