Astrea Evolve AA20CRK Посібник із заміни - Сторінка 12
Переглянути онлайн або завантажити pdf Посібник із заміни для Промислове обладнання Astrea Evolve AA20CRK. Astrea Evolve AA20CRK 19 сторінок. Wetted flow path for 200mm and 250mm chromatography columns
Reassembly of 200mm and 250 column.
Reassembly of the column is the reverse of disassembly.
Tube Assembly
1. The orientation of the tube is shown by the fitted scale label.
2. The buffer seals should be place on the outside diameter of the tube at a distance
approximately 2cm from the end of the tube. They should be orientated as shown in the
diagram below.
Figure 1.6 Diagram showing the location of the fixed bed support
3. Locate the tube in the bottom column flange. Ensure it is located centrally and evenly
4. Replace the top column flange and locate the tube support bolts.
5. Locate the upper and lower buffer seals into the bottom and underside of the top
column flange.
6. Using the correct Allen key tighten the Tube support Rod bolts located in the top
column flange.
Fixed Assembly
1. Install to antijet in the flowcell by carefully locating the 3 pins into the ribbed face of the
flowcell.
2. Locate the flowcell on the cell backing plate and replace the fixing bolts and tighten.
3. Install the process flowtube into the back of the flowcell. Ensure the flowtube seal is
located. Tighten process flowtube using correct tools.
4. Refit the pipespool clamp and pipespool elbow.
5. Install the bed support/seal assembly on to the flowcell by carefully locating the bed
support seal onto the flowcell. The bed support should be fitted with the smooth side
facing into the column. See Figure below.
Figure 1.7 Diagram showing the location of the fixed bed support
Top Buffer
Seal
Bottom Buffer
Seal
Seal
Rough Side
11
Smooth Side
Flow cell