– Be sure all components of the spark ignition system are installed and functioning
properly.
– Be sure all valves are installed in the proper location and correctly oriented relative
to the flow direction.
9.6 Prepare for adjustment
After installation of the burner system components is complete, the following steps
should be followed in order to prepare for adjustment:
– Set the air flow switch so that it drops out at 50% below the maximum pressure of
the process air.
– Set the low gas pressure switch at 50% below the gas pressure measured at the
inlet to the main gas valve train.
– Set the high gas pressure switch at 50% above the gas pressure measured at the
inlet to the main gas valve train.
– Try to ignite the burner before the purge and other timers have finished their
cycles. Make sure that the flame monitoring system indicates a flame failure.
– Trip out the pressure switches and other limit interlocks. Make sure that the main
gas valve train closes.
– If the simulated limit condition or the simulated flame fault cannot be responded at
the specified fault response time, the fuel system needs to be turned off to correct
the existing problems.
10. Burner Maintenance
Preventive maintenance is the key to a reliable, safe and efficient combustion system. The
core of any preventive maintenance system is a list of periodic tasks. These are guidelines
only. The customer should make the final determination on maintenance intervals and
tasks to be performed while considering the working environment.
System regular safety audit must be taken out, including gas leakage check no longer than
every half a year. If necessary, the frequency of audit should be increased. Leak detection,
control functions of the equipment must be included in the scope of audit. Only Anderson
technicians or those who are been trained and qualified by Anderson, as well as other
relevant professionals, can maintain the burners. All valves, especially ball valves, must be
slowly open or close when switching in order to prevent pressure shock in pipe.
10.1 Half a year checklist
– Inspect the flame sensing devices for good condition and cleanliness.
– Check for proper air and gas pressures.
– Test all the system alarms for proper response signals.
– Check and clean igniter electrodes.
– Check valve motors and control valves for free, smooth action and adjustment.
– Check for the proper operation of ventilating equipment.
– Test the interlock sequence on all safety equipment. Manually force each interlock
to intentionally fail while at the same time noting if related equipment closes or
stops as specified by the manufacturer. Test the flame safeguard by manually
shutting off the gas to the burner.