SKYCHARGE – TECHNICAL DOCUMENTATION
Page 4

2 INSTALLATION

2.1 Mounting

Fix the charging station on the column requires a minimum of two people.
Fix the column on the concrete base with 4 threaded rods M10 according to the following diagram.
Do not forget the flat washers.
Electrical introduction is done through the left opening size 100x50mm with 1600 mm cable.
Bottom view:
Electrical introduction
Concrete base :
A concrete base have to be settled before
receiving the charger with the following
dimensions : 700 x 400 x 150 mm
Electrical cable