Downee Spring Gate 설치 매뉴얼 - 페이지 10

{카테고리_이름} Downee Spring Gate에 대한 설치 매뉴얼을 온라인으로 검색하거나 PDF를 다운로드하세요. Downee Spring Gate 14 페이지. Double gates

CONNECT MOTOR TWO
1.
Dig a channel for Conduit.
2.
Run the Figure 8 cable
through Conduit.
3.
Connect Figure 8 cable to red
& blue cables on both Motors.
Use 0.75mm Figure 8, 2-core cable in conduit buried across driveway
NOTE
(not supplied). 24V cable is harmless to humans and animals. Bury
conduit at a depth you're comfortale with.
4.
Place the fuse (inside Battery Box door) into the fuse holder on the red
power cable. The batteries are fully charged so it may spark. That's OK,
24V is completely safe.
5.
With the carton still covering the solar panel, connect the black and red
power cables to the Solar Panel and Battery. The digital screen on
the motor's control board and solar controller screen will light up.
6.
Cable tie the power cables to the post.
Red & Blue
Cables
Motor One
7