Cisco ONS 15454 포장 풀기 및 설치 - 페이지 9
{카테고리_이름} Cisco ONS 15454에 대한 포장 풀기 및 설치을 온라인으로 검색하거나 PDF를 다운로드하세요. Cisco ONS 15454 42 페이지. Four-shelf and zero-shelf bay assembly
Cisco ONS 15454에 대해서도 마찬가지입니다: 설치 지침 매뉴얼 (22 페이지), 설치 (32 페이지), 설치 (32 페이지), 포장 풀기 및 설치 (40 페이지)
Raised Floor Plan
Level Equipment
The raised floor is laser-leveled at the time of the floor installation, so no leveling blocks or shims should
be necessary to level the frames. This is especially important in seismic zones 2B and higher, because
leveling blocks will cause a rocking motion of the frames during an earthquake.
Cut and Drill Removable Floor Tile
Mark the removable floor tile for the cable access to the rack using one of the following methods: the
Step 1
floor cutout template included in the accessory kit (700-14208-XX) that ships with the zero-shelf bay
assembly, the diagrams in
mark the tile from the base of the frame or cabinet.
Mark the tile for the frame anchoring holes.
Step 2
Remove the tile.
Step 3
Cut cable access holes.
Step 4
Step 5
Drill the anchoring holes through the tile in an area away from the equipment to ensure the equipment
area is not contaminated with metal shavings or debris.
Note
Note
78-13271-05
Figure
6, a floor plan drawing, or place the frame in the proper footprint and
If the floor plan identifies a future frame on the same tile as the one you are adding a frame to,
you must drill and cut the tile for the future frame at this time because you cannot remove the
tile later.
It will be necessary to use alternate anchoring holes in the event the primary holes are obstructed
by the stringers that support the removable tile.
Unpacking and Installing the Cisco ONS 15454 Four-Shelf and Zero-Shelf Bay Assembly
Installation Instructions
9