Warning
Step
1
Remove the screw on
the electrical box.
2
Unfasten the hook and
remove the shield plate.
3
Unfasten the 2 hooks
on the top and remove
the signal receiver unit.
10
Be sure to wait for 10 minutes or more after turning off all power supplies before
disassembling work.
Procedure
Electrical box
Shield
plate
Hook
(R17747)
(R13224)
Signal receiver
unit
(R2781)
Si041254EE
Points
The shield plate also has 2
hooks on the upper side (at
the back).